SAFETY System Checkout
Your SUPERB® Dryer has many SAFETY controls interlocked to stop the Dryer if a hazardous condition develops. The following controls stop all Dryer functions immediately and necessitate a manual restart of the Dryer. Your Dryer installation (including Plumbing Train Connections see main menu) should not be considered complete until a SAFETY Systems checkout is run to see that all SAFETY systems are in working order. This should be done before initial startup. It should also be done at the beginning of each season and any components replaced if necessary.
Red Power Light (optional)
Turn the Dryer Disconnect Circuit Breaker ON. Observe the red light on the front of the Control Cabinet.
Fuel Line Shutoff Valves (optional)
Vent Pipe Outlets
1
2
Upper Plenum RTD and Hi-Limit Sensor
The single line on the opposite side is the (Upper Plenum) Static Pressure Tube.